2024 Turnaround: Fuelled by people

March 27, 2024

People fuel our annual Turnaround. 2024 Turnaround is certainly no exception.

This year’s project will officially get underway the first week of April 2024 and is expected to run for up to 47 days. During this time, we will welcome an additional 2,200 skilled trades personnel to our facility. As a team, we will work together to perform preventive maintenance, renovations, and upgrades as part of the multi-million-dollar project – ultimately allowing us to continue safe and reliable operations.

Protecting our people and our community

The success of our Turnaround is ultimately tied to our safety performance.

Safety is always the most important aspect of how we operate and how we conduct our business. It is our collective responsibility as workers, support staff and contractors, to keep our site and our community safe. We’re committed to working closely with our people, partners, and local community to ensure that safety remains our top priority.

Putting people to work to keep everything working

We continue to emphasize the importance of planning and executing the project safely, while ensuring work is done to the highest standard. It is a time of heightened awareness and detailed planning. This includes:

  • Performing safety critical maintenance and removing/reducing process hazard/risk
  • Meeting regulatory (codes and standards) requirements
  • Conducting equipment integrity inspections and repairing/replacing malfunctioning equipment
  • Completing equipment replacements, upgrades and preventative maintenance programs
  • Changing catalyst to maintain operational targets

2024 Turnaround – just the facts

  • An investment of more than $140 million.
  • There will be an estimated 3,200 employees on site during peak times, including an estimated 2,200 additional skilled trades personnel.
  • An estimated 840,000 person hours will be required to complete the project.
  • Approximately 31 cranes will be used.
  • Work will be performed on hundreds of pieces of equipment.