2025 Turnaround: A catalyst for success

March 14, 2025

This year’s project will officially get underway the first week of April 2025 and is expected to run for up to 45 days. During this time, we will welcome an additional 800 skilled trades personnel to our facility. As a team, we will work together to perform preventive maintenance, renovations, and upgrades as part of the multi-million-dollar project – ultimately allowing us to continue safe and reliable operations.

Investing in safety, investing in our community
The success of our Turnaround is ultimately tied to our safety performance.

Safety is always the most important aspect of how we operate and how we conduct our business. It is our collective responsibility as workers, support staff and contractors, to keep our site and our community safe. We’re committed to working closely with our people, partners and local community to ensure that safety remains our top priority.

Putting people to work to keep everything working
We continue to emphasize the importance of planning and executing the project safely, while ensuring work is done to the highest standard. It is a time of heightened awareness and detailed planning. This includes:

  • Performing safety critical maintenance and removing/reducing process hazard/risk
  • Meeting regulatory (codes and standards) requirements
  • Conducting equipment integrity inspections and repairing/replacing malfunctioning equipment
  • Completing equipment replacements, upgrades and preventative maintenance programs
  • Changing catalyst to maintain operational targets

2025 Turnaround — just the facts

  • An investment of more than $90 million.
  • There will be an estimated 1,000 employees on site during peak times, including an estimated 800 additional skilled trades personnel.
  • An estimated 510,000 person hours will be required to complete the project.
  • Work will be performed on hundreds of pieces of equipment.